Current R&R Projects

 

LWD Projects Currently Under Construction:

 

Project Name: Sylvan Park Water Main Replacement Program, Phase 2

Job No.: 0611
Work Order No.: 21066
District Project Manager: Craig Gibson
Engineer: Parametrix
Engineer’s Estimate: $640,000

Scope of Project:
Furnishing and Installing approximately 3,700 linear feet of 8-inch-diameter PVC pipe, three fire hydrants, valves, appurtenances, replacement and reconnection of 66 water services, connections to the existing water main and restoration. The Contractor shall provide and install all water system materials including water main, fittings, valves, fire hydrants, and water service materials.

Invitation to Bid published in DJC: 2/20/17
Invitation to Bid published in TNT: 2/20/17

Walk-thru date, time, and location: Tuesday, February 28, 2017 @ 10:00am, at the north end of the project at the intersection of 88th Street S and Gayle Avenue S.

Bid Opening: 10:00am on Tuesday, March 7, 2017, District Board Room

Project Awarded to Contractor with Lowest Bid: Johnson & Maddox Construction Co., Inc.

Project completion info: This project is currently under construction.

Customer Letter: Sylvan Park Water Main Replacement Project, Phase 2.

 

____________________________________________________________________________

 

Project Name: Thorne Lane Project from Portland Avenue to Spruce Street

Job No.: 0628
Work Order No.: 21131
District Project Manager: Craig Gibson
Engineer: RH2 Engineering, Inc.
Engineer’s Estimate: $487,000

Scope of Project:
Furnishing and installing approximately 1,450 linear feet of 8-inch diameter ductile iron pipe, fire hydrants, valves, appurtenances, replacement and reconnection of water services, connections to the existing water main and restoration. The Contractor shall provide and install all water system materials including water main, fittings, valves, fire hydrants and water service materials. LWD will provide water meters.

Invitation to Bid published in DJC: 11/7/16
Invitation to Bid published in TNT: 11/7/16

Walk-thru date, time, and location: Tuesday, November 15, 2016 @ 9:00am, on site.

Bid Opening: Until but not after 10:00am on Tuesday, December 6, 2016, District Board Room

Project Awarded to Contractor with Lowest Bid: Pape and Sons Construction, Inc.

Project completion info: This project is currently under construction.

 

____________________________________________________________________________

 

For a list of upcoming R & R projects, please click here.